Raft footing, also known as mat footing, is a large continuous slab designed to support multiple columns and walls. It is used where the soil bearing capacity is low, or loads from the structure are distributed over a large area. Preparing the Bar Bending Schedule (BBS) for raft footings ensures proper estimation of steel requirements and aids in efficient construction planning.
Given:
Raft size: 8m x 6m x 0.6m Cover: 75mm Main bar diameter: 20mm Distribution bar diameter: 16mm Spacing of bars: 200mm c/c
Step 1: Calculate Number of Bars
Effective length = Total length - 2 x Cover = 8000mm - 2 x 75mm = 7850mm Effective width = Total width - 2 x Cover = 6000mm - 2 x 75mm = 5850mm Number of main bars = (Effective width / Spacing) + 1 = (5850 / 200) + 1 = 30 bars Number of distribution bars = (Effective length / Spacing) + 1 = (7850 / 200) + 1 = 40 bars
Step 2: Calculate Bar Length
Length of each main bar = Effective length + 2 x Cover = 7850 + 2 x 75 = 8000mm or 8m Length of each distribution bar = Effective width + 2 x Cover = 5850 + 2 x 75 = 6000mm or 6m
Step 3: Total Steel Quantity
Total length of main bars = Number of main bars x Length of each main bar = 30 x 8 = 240m Total length of distribution bars = Number of distribution bars x Length of each distribution bar = 40 x 6 = 240m
By preparing an accurate BBS for raft footings, structural engineers can ensure material optimization, cost efficiency, and structural stability.